Letter to the Editor: Sound View Property Owner Asks Old Lyme to ‘Play Fair’ in Sewer Installation Charges

To the Editor:

I am a newly appointed member of the OLWPCA (Old Lyme Water Pollution Control Authority) but am writing here not as a WPCA representative but as a property owner in Old Lyme.

My property in ‘Area B’ – near the railroad tracks – was recently appraised at $210,900. It consists of 712 square feet, 2 bedrooms, 1 bath. It is seasonal. 

Let’s assume for the moment that all current received bids hold without increases once they expire June 30th and let’s assume for the moment that Miami Beach receives a bid this fourth go-around and Old Lyme Shores receives an acceptable bid in its third go-around. 

My property is assigned 1 [one] Equivalent Dwelling Unit [EDU.] Based on the Chairman Cinami’s latest figures and after an assumed 50% reimbursement is applied, I will owe $38,000 for construction fees. In a written quote from B&L, I will owe an additional $8,700 to decommission my engineered septic system and run a new line to the curb. Then of course, there’s those additional town contractual fees of the project; 1.3 million owed to East Lyme and New London to connect,  plus maintenance, management, bookkeeping, bioxide, easements, legal, consulting fees and repairs, etc. These additional charges cannot be divided by 270 EDUS because the undeveloped lots (including the bus stop!) equate to 9 EDUs that must be subtracted from maintenance billing.

Furthermore, the Chairman has said that some properties will be granted variances to delay connecting so those properties as well, cannot be billed for maintenance until some later date. Hard to guess what all that extra maintenance and contractual fees will cost me then when I connect, but let’s say conservatively it totals another $600 a year, plus $400 a year for actual usage based on flow. In summary then, it’s $1000 a year in contractual and maintenance and usage fees for the next 20 years or $20,000 (we’ll set aside that these contracts have escalation clauses after year 1). I’m up to $66,700 for a sewer to replace my perfectly fine engineered system on my property that is appraised at $210,900. That’s 31.63% of the appraised value. I will be paying minimally $3,445 per year for the next 20 years for something I do not need.

You call that fair? 

There are 29 single family homes in Area B. Sixteen are appraised less than $255,000. They will all be charged just like me. Nadeau Associates stated that the value added to a residential property [after installation of a new sewer system] is 7% and the OLWPCA expert Christopher Kerin [of the real estate valuation and advisory firm Kerin & Fazio LLC] says it’s 10%. All of the 29 residential homes in Area B and the majority of the commercial properties, will fail that test. 

And given the following quote from Graham Stevens [of the Department of Energy and Environmental Protection] in 2023 to OLSSPA [Old Lyme Shoreline Sewer Project Alliance] that, “Determination that project area user charges to finance the project in excess of 2% MHI [Median Household Income] are unaffordable” indicates that only the medium income of Area B/Sound View should be considered – not the town. I am betting that all of Area B, and Sound View will fail that 2% income affordability test if it is applied the right way. Just because our properties are located near the railroad tracks, does not give you the right to railroad us. Play fair Old Lyme!   

Sincerely,

Brian Cornell,
Old Lyme.

TOP STORY: Old Lyme WPCA Chair Cinami Seeks to Get Sewer Project Finally Flowing, Requests Additional $7.6 Million

Old Lyme Water Pollution Control Authority Chairman Steve Cinami addresses a $7.6 million bond authorization request for sewers to First Selectwoman Martha Shoemaker, center, Selectman Jim Lampos, left, and Selectwoman Jude Read, right.

OLD LYME–6/22 UPDATED: Headline amended: Six years ago, a $9.5 million request to install sewers in the Sound View Beach area got the go-ahead from voters at a town-wide referendum – but the project stalled.

Now, amid inflation exacerbated by the COVID pandemic and other factors, the Old Lyme Water Pollution Control Authority (WPCA) is back with a request for another $7.6 million. 

The state-led, decades-long charge to clean up Long Island Sound by ridding the area of septic systems involves a plan to require residents of three private beach associations and the public Sound View Beach community to install sewers. Continued concerns about the cost of the project and successive rounds of construction bids coming in higher than anticipated have dragged out the process.

Steve Cinami, chairman of the Old Lyme WPCA, visited the Board of Selectmen and Board of Finance this week to plead for approval to go to referendum for the bond authorization necessary to support the Sound View portion of the project. But selectmen balked at the lack of information about how the project will affect the Sound View residents who will have to repay the loan.

Old Lyme officials all along have said the cost of the Sound View project will be borne by the system’s users, not the town’s tax base. 

This time around, significant additional funding from the state and federal government will leave those users responsible for about $8.5 million of the $17.06 million project, which Cinami has emphasized is less than the amount requested at the 2019 referendum. 

He said the new numbers shake out to about $26,000 over 20 years, or $1,932 per year, for a property owner whose house has one bathroom, a kitchen, and four bedrooms or less.  

In August of last year – before the latest round of bids came back and before state and federal funding was secured – Cinami at a public meeting told residents the WPCA was estimating the cost to a user would be about $22,556 over 20 years, or $1,368 a year, for a similarly sized home. 

Assessing ‘affordability’

Selectman Jim Lampos at Monday’s selectmen’s meeting asked for more specifics about fees in addition to the annual project payments for which users will be responsible. He said connection costs and future capital spending for infrastructure improvements in the system flowing through East Lyme into New London will affect user’s sewer bills here in Old Lyme. 

“Before we go to a referendum, I think we have to give the property owners a clear idea of what the affordability is going to be,” he said. “And the taxpayers are going to want to know this before going to a referendum. They’re going to ask for it.”

Cinami estimated the average yearly fee would be around $500 per year in the Sound View area. Beyond that, he said he would have to “try” to develop a rough cost structure. 

State Department of Energy and Environmental Protection (DEEP) Project Engineer Carlos Esguerra last year said the agency sets the amount that residents can reasonably be expected to spend at 2% of the town’s median income, which he identified at the time as $122,000. That equated to $2,440 a year.

There is also a state law specifying a town cannot assess property owners for any amount higher than the percent increase in the property value attributed to the sewers. He said an assessor hired by the Old Lyme WPCA before the previous referendum estimated sewers would increase home values between 10 to 12%. 

Documents from the Sound View Coalition, a grassroots group opposing the sewer project, show an assessor hired in 2020 by the group found sewers would increase residential property values by 7% and commercial properties by 10%.

Cinami, who has been criticized for his abrasive manner at meetings, also heard complaints at Monday’s meeting from Shoemaker and Old Lyme WPCA member Dennis Melluzzo about the chairman’s alleged attempts to quell questions and dissent. 

Shoemaker said she was made to feel uncomfortable asking questions at the June WPCA meeting, while Melluzzo described feeling disrespected by Cinami while speaking up at last month’s WPCA meeting. 

Cinami said he was just trying to run an efficient meeting. 

“I feel, maybe it’s a misperception, but I feel as though I’m trying to get stuff across and I’m interrupted on a constant basis by members.”

He told Shoemaker he was sorry if she took offense, and said he owed Melluzzo an apology as well. 

Capital Costs

At Tuesday’s finance board meeting, member David Kelsey expressed concern about the financial impact of any large-scale capital upgrades that could happen in the future at the New London wastewater treatment plant into which Old Lyme’s sewage will flow. 

He said he’s heard for the past 10 years that DEEP was pushing for the installation of sewers in Old Lyme “because they wanted more users to spread the cost of upgrades in New London.” 

Cinami said he wasn’t aware that the city was on the verge of any major capital projects. 

New London Director of Public Utilities Joseph Lanzafame in a Wednesday phone call disputed Kelsey’s characterization of the situation. 

“There’s no truth to that. Not from our standpoint,” he said. “Somebody else may have other motivations, but from our standpoint, the contribution that Old Lyme is going to give towards the facility is very marginal.” 

A contract between New London and the four beach communities signed late last year calls for the beach associations to pay 1.2% of annual treatment plant capital costs and the town to pay 0.5%.

He estimated the city has spent $15 million over the past 10 years, but could not predict what the future holds in store. 

“But as far as major upgrades, I mean, we’re not looking at hundreds of millions of dollars of work to be done,” he said. 

He said the city does not have plans to upgrade the plant to be able to handle additional flow, which he described as an extremely difficult undertaking. But if that kind of upgrade did happen, he added that Old Lyme ratepayers would not be affected unless the beach associations or the town wanted to purchase some of the increased capacity. 

The current contract with New London allows the beach associations to send up to 120,000 gallons of sewage per day to the treatment plant and the town to send up to 50,000. They have the right to purchase up to an additional 130,000 gallons per day as more people in the beach communities tie into the system.

Lanzafame said he’ll be happy if Old Lyme doesn’t ask for additional capacity in the future. 

“I mean, I’m going to be quite frank. That’s just what it is. Wastewater capacity is a big deal, and it’s just not unlimited,” he said. 

Back at the finance board meeting, Kelsey predicted the costs to each user – including the minimum $1,932 payment homeowners will need to pay for 20 years, the cost of tying into the system, the annual fees and the increased tax bills from their new property values – are likely to result in angry residents. 

“It’s not going to be pleasant when all these numbers come out, is my basic point,” he said. 

While Cinami acknowledged residents in the affected areas will be required to hook up to the system, he added a caveat. 

“There are some new (septic) systems down there that cost sixty thousand dollars; We will probably not have them hook up immediately,” he said. “But any any system that’s in variance, which is, I would say, 97% of all the systems down there, will have to hook up.” 

Next Steps 

In addition to asking for more information on the financial impact for Sound View residents, the Board of Selectmen emphasized that the details of a Cost Sharing Agreement between the beach associations and the town must be finalized before they will ask residents to authorize more spending at a referendum. 

Another issue still outstanding revolves around the portions of the sewer project to be undertaken by the Miami Beach and Old Lyme Shores Beach Associations, which Cinami said have not yet gone out to bid. He said the beach communities’ project officials, who are waiting for approval by the state DEEP before opening the bid process, are hoping to make their selections by the end of July.

Cinami assured selectmen that winning bids received earlier this year for the Sound View work will remain valid through October, though he acknowledged the bidder selected to build the system’s shared pump station has not formally committed to keep his bid open that long. 

Shoemaker said Cinami’s request to schedule a referendum for August 14 won’t be possible because the traditional polling location in the middle school is being renovated and will not be available.